How to create an internal change order?

Use internal change orders to forecast budgets by adding or subtracting from individual cost codes based on actual expenditures and future predictions or move money from one cost code to another. (This will change Profit but not contract amount)

Changes Change Orders 

Global Dashboard CO-3

Internal CO Tasks > Create Internal CO

GD Create ICO

Add or subtract to any item you need to adjust and add an explanation to create an audit trail.

Click Save and click Return to Change Order List.

ICO screen 1

To view affect on overhead and profit, print the budget report. Click on Reports > under the Accounting column > Budgets, click on Budget Report. Below is an example.

Budget report